AUGUST REINERS has reached a major interim milestone at the Hamburg Harbor Railway Tunnel. With the partial dismantling of the bored pile wall along the rail line, the partial breakthrough from west to east has been achieved. For the first time, there is now a continuous line of sight from the eastern excavation pit into the western section of the tunnel.
The structure is being built as part of the A26 federal highway (Construction Lot 4.2) as an underpass beneath the Hamburg Harbor Railway. It is being constructed using the cut-and-cover method as a two-cell frame, with AUGUST REINERS carrying out the work as part of the ARGE Hafenbahntunnel Hamburg consortium. Of the tunnel sections to be built, 172 meters have already been completed.
In the upcoming construction phases, a submerged concrete floor with a volume of approximately 7,825 m³ will be poured in the approximately 5,215 m² excavation pit on the east side, before construction proceeds on the remaining approximately 108 m of tunnel and an operations building.
This milestone is the result of close and solution-oriented collaboration among all project participants. AUGUST REINERS would like to thank the client, DEGES (acting on behalf of Autobahn GmbH des Bundes), its joint venture partner Bauer Spezialtiefbau, and the subcontractors involved. The participants jointly celebrated the milestone on site.