In Wolgast, in Western Pomerania, Federal Highway B 111 leads to the Baltic Sea island of Usedom. Currently, traffic there crosses via a bascule bridge that opens several times a day to allow ships to pass. This regularly interrupts road traffic—resulting in correspondingly heavy traffic congestion in Wolgast. The new bypass, featuring the New Peene Bridge, is set to change that in the future. With a clearance height of 42 meters, ship and road traffic will be able to move independently of one another.
The bridge is 1.5 km long and consists of 18 spans constructed using a steel-concrete composite design. It spans 252 meters across the Peenestrom between two pylons. The project owner is the Schwerin Road Construction Authority, acting on behalf of the state of Mecklenburg-Western Pomerania. AUGUST REINERS is carrying out the reinforced concrete work on the mainland and on the Usedom side on behalf of Implenia. This includes the two abutments at axes 10 and 190 and the four piers at axes 20 through 50.
We have now reached our first major milestone: The abutment at Axis 10 has been completed in preparation for the steel construction and bridge advancement. This clears the way on the mainland side for the assembly of the steel superstructure.
The piers are also visibly rising. The first sections have been poured with concrete, and the climbing formwork is now moving upward section by section. Each time, the formwork and work platforms are moved up to the completed section of the pier. This allows work to be carried out safely from the ground, even at great heights, without the need for scaffolding. The pier’s geometry poses a particular challenge: the groove, which measures 4 × 5 meters in cross-section, widens toward the top and is formed using structural formwork.
The next important step following the abutment will take place later this month: With the completion of the pier head, Pier 20 will be handed over to the steel construction team. This will allow the sliding of the steel superstructure to continue.